InQuik: An Australian success story in modular bridge construction

Unique modular bridge construction by Australia’s InQuik is finding a new audience in the U.S.

InQuik, an Australian company, has developed a unique method for building modular bridges that is gaining traction in the United States. The InQuik system consists of prefabricated formwork trays with reinforcing steel, placed on-site and filled with concrete to create robust, cast-in-place structures. This approach significantly reduces construction time compared to traditional methods and ensures high-quality, durable bridges.

Logan Mullaney, co-founder of InQuik, President – InQuik USA.
Logan Mullaney, co-founder of InQuik, President – InQuik USA.

Founded approximately eight years ago, InQuik has built over 200 modular bridges in Australia. The system was developed by Bruce and Logan Mullaney, along with Jim Howell. Initially aimed at improving modular housing transport systems, the team identified other uses for the technology, leading to the current bridge system.

InQuik’s patented technology utilises prefabricated moulds made from sheet steel with a reinforcing rebar matrix. The formwork, made from Magnelis, a corrosion-resistant solution from ArcelorMittal Europe, remains in place after the concrete is poured, providing aesthetic appeal and additional protection. This system allows for quick installation using low-skilled labour and is designed for a 100-year service life, potentially doubled by the use of Magnelis without significant maintenance.

“This is a system that certainly has the potential to complement offsite projects where ease and speed of installation are a priority,” said InQuik National Sales Manager, Robert Lindley.

As first reported in Engineering News-Record, the system has also been successfully implemented in the United States, starting with Eau Claire County, Wisconsin. The first InQuik bridge, a 9-metre-long, 8-metre-wide structure, was completed in a month, compared to the usual three-to-four-month timeline for traditional bridges.

Watch InQuik’s modular bridge story of Parsonage Creek, NSW

West Virginia also plans to use the system, with state Department of Transportation Commissioner Jimmy Wriston praising its potential for accelerated bridge construction, especially in disaster recovery scenarios.

“I think it’s kind of spectacular,” he says of the technology. “We’ve always been interested in Accelerated Bridge Construction. This fits in that mold. You can load components up, haul them to the jobsite on a truck and deliver quickly. I think it will be a boon, especially after flooding or tornadoes.”

The InQuik modular bridge system eliminates the need for longitudinal joints in precast bridges, allowing for integral pouring of the bridge deck and stems. The product range includes deck panels, abutments, wing walls, headstocks, and blade piers, all designed for efficient transport and installation.

Mike Culmo, chief engineer at CHA in Albany, New York, recommended the system to the Utah Department of Transportation, highlighting its ability to prefabricate everything except the concrete. “It allows you to prefabricate everything but the concrete,” he says. “You can erect [the elements] with small equipment. Usually, you’d need big cranes to lift heavy precast pieces. [Inquik] solves the problem of weight and connections between the elements … you don’t have to build formwork or falsework.”

See: https://inquik.com.au/