South Melbourne Women’s, Middle Park and Power House Rugby facilities delivered with reduced site impact.
Partner content
At Modular by SHAPE’s Albert Park project, FTA helical screw piles were deployed across three modular facilities within the precinct, including the South Melbourne Women’s Soccer Club, Middle Park Soccer Club, and the Power House Rugby Union Football Club facility. Foundation selection was shaped by site constraints, programme pressures, and the need to deliver within a tightly controlled event environment. (Main image: A volumetric module for the Power House Rugby facility is lowered onto FTA helical screw piles at Albert Park.)
The works formed part of a broader redevelopment within the Albert Park precinct, where Modular by SHAPE was tasked with delivering a mix of permanent and relocation-ready buildings. FTA’s involvement extended across all three, building on a prior working relationship that also included projects delivered for the Victorian School Building Authority.

For Zarko Milakovic, General Manager – Modular (Victoria), the decision to adopt screw piles was made early and driven by logistics as much as engineering.
“We originally looked at how we were going to break down the methodology of construction, and the priority was to minimise time on site,” he says. “That meant reducing the number of trucks coming in and limiting the number of contractors required to deliver the foundation system.”
“Soil conditions allowed for screw piles, but the bigger factor was speed. FTA could install the system in a couple of days. If we went down a bored pier path, you’re drilling, pouring concrete, and then waiting for curing. That just wasn’t going to work within the programme.”
Reducing site impact in a constrained environment
The Albert Park precinct presented a set of constraints not typically encountered on standard projects. The construction programme had to align with Formula One infrastructure works, including restricted delivery windows and full site shutdown periods.
“We were right in the middle of a sensitive period where deliveries were limited,” Milakovic says. “Reducing traffic into that space was critical. Screw piles gave us a way to install quickly and then get off site.”
Cameron Aitken, Group Manager – Modular, sees the benefit extending beyond programme.
“It’s not just about speed,” he says. “It’s about reducing complexity. On a typical project, we might be dealing with 30 to 40 subcontractors. If you can replace multiple trades with a single contractor delivering a complete system, that has real value for us operationally.”
FTA’s involvement during the design phase was central to that outcome. By working alongside Modular by SHAPE’s engineers from the outset, the foundation system could be integrated with the structural steel and volumetric modules before manufacturing began.
“We engaged FTA while we were still engineering the footing system,” Milakovic says. “They worked alongside our engineers to make sure their system aligned with our building. That meant when we got to manufacturing, we already understood how the modules would interface with the screw piles and the level master system.”
FTA helical screw piles installed across the Albert Park precinct ahead of modular building installation for the South Melbourne Women’s Soccer Club, Middle Park Soccer Club and Power House Rugby facilities.
Coordination and tolerance in modular delivery
FTA’s screw pile and Level Master system allowed Modular by SHAPE to level modules immediately after installation, reducing the need for secondary works on site. However, the integration of volumetric modules with screw piles introduced tight tolerance requirements.
“When the modules land, they have to sit directly over the centre of the pile, because that’s where the load is transferred,” Milakovic says. “There’s not a lot of tolerance in that. You need to be very disciplined with survey and coordination. We double-check everything, including using multiple surveyors where required.”
The system also reduced exposure to weather-related delays and site risks.
“With bored piers, you’re dealing with open excavations, potential water ingress, and curing delays,” Milakovic says. “With screw piles, you can install one day and land modules the next, assuming no issues. That removes a lot of uncertainty.”
Aitken frames this in terms of broader project delivery.
“It de-risks the programme,” he says. “It de-risks the contract. And it reduces the number of moving parts we have to manage.”

Cost, value and repeatability
While screw piles can carry a higher upfront cost compared to traditional bored piers, SHAPE views the decision through a broader lens.
“On paper, screw piles might be slightly more expensive than a traditional bored pier system,” Milakovic says. “But that’s just the line item. When you factor in time savings, reduced coordination, and fewer contractors, the value becomes clear.”
The system is not universally applicable. Soil conditions and site-specific constraints still determine suitability, and Milakovic notes that FTA are upfront when their system is not appropriate.
But where conditions align, the preference is clear.
“If the site allows it, we would lean towards screw piles,” he says. “The time savings and the reduced coordination required on site outweigh the traditional approach.”
Across the three facilities at Albert Park, including the permanent Power House Rugby facility and the relocation-ready buildings for Middle Park and South Melbourne Women’s Soccer Club, the use of FTA screw piles enabled Modular by SHAPE to maintain programme certainty while working within one of Melbourne’s most constrained construction environments.