Supreme Court rejects Built application in modular prison cell dispute

Justice Nichols dismisses builder’s bid for declarations in case involving Fleetwood manufactured prison cells.

The Supreme Court of Victoria has dismissed an application by builder Built Pty Ltd in a dispute linked to defective modular prison cells installed at the Metropolitan Remand Centre in Melbourne. (main image: Cell accommodation blocks under construction at Fleetwood’s manufacturing facility for the Victorian Government’s Prison Infill Expansion Program. Credit image Fleetwood.)

The case relates to prefabricated prison cells manufactured by Fleetwood and installed at the facility as part of the Victorian Government’s Prison Infill Expansion Program. The cells were delivered to site and installed by Built under a construction contract with Victorian Correctional Infrastructure Partnership (VCIP), the project company responsible for delivering the works under a broader agreement with the State of Victoria.

Fleetwood was awarded a $41.5 million contract in September 2020 by the Victorian Department of Justice and Community Safety to manufacture and supply 460 modular prison cells for the program, which involves capacity expansions across five Victorian correctional facilities.

At the time of the contract award, then managing director and chief executive Brad Denison said the agreement aligned with the company’s strategy to expand its modular cell capability beyond New South Wales and into other Australian jurisdictions.

Justice Lisa Nichols noted in the judgment that VCIP was responsible for delivering the prison expansion works under its agreement with the state before subcontracting the design and construction works to Built.

Dispute over defects in modular cells

According to the judgment, the dispute emerged in 2023 after defects were identified in a number of modular cells installed at the facility.

Justice Nichols stated that “in 2023, a dispute arose regarding alleged defects in modular cells.”

Built disputed responsibility for those issues, arguing that the defects existed before installation. In correspondence referenced in the judgment, Built stated that the modular cells “contained extensive rust and mould on delivery to the Metropolitan Remand Centre site”.

The disagreement led to a series of contractual notices between VCIP and Built relating to responsibility for rectification works, extensions of time for practical completion and claims connected to delays on the project.

Court rejects request for declarations
Built subsequently applied to the Supreme Court seeking declarations that the disputes raised by VCIP did not constitute “Linked Claims” or “Linked Disputes” under the construction contract governing the project.

That contractual mechanism effectively links disputes between Built and VCIP to related disputes between VCIP and the State, meaning downstream disputes may be paused while upstream claims are resolved.

Built also argued that elements of the contractual dispute framework were ineffective under provisions of the Building and Construction Industry Security of Payment Act 2002.

Justice Nichols rejected those arguments.

The judgment found that the disputes identified in VCIP’s notice remained valid within the contractual framework governing the project and continued to exist within the dispute resolution mechanisms set out in the contract.

Justice Nichols concluded that the application should be dismissed, stating that “for the reasons that follow Built’s application for declaratory relief is refused.”

The ruling leaves the contractual dispute processes in place while related arbitration proceedings between the project parties continue.

Find the Supreme Court of Victoria’s findings HERE